Overhead cranes, known for their high load capacity, stable operation, and wide applicability, are extensively used across industries such as steel and metallurgy, machinery manufacturing, warehousing and logistics, and power and energy. They perform frequent and critical material handling tasks. In real production environments, overhead cranes often operate under heavy loads or continuous duty conditions, making their safety and reliability directly related to personnel safety and production efficiency. For this reason, overhead crane load testing must be carried out rigorously before overhead cranes are put into service.
Load testing is not only used to verify the actual load capacity and structural strength of the equipment, but also to comprehensively check the performance of the hoisting, traveling, braking, and safety systems under rated operating conditions. It helps identify potential risks in advance and ensures that the crane complies with relevant standards and design requirements. Therefore, load testing for overhead cranes is not an optional procedure, but an essential step throughout the transition from manufacturing to commissioning. It forms a critical foundation for ensuring safe, stable, and long-term operation.

Load testing runs through the entire life cycle of an overhead crane. During the manufacturing stage, it is a key element of factory quality control. During installation and commissioning, it serves as a critical basis for acceptance and handover. During operation, especially after major repairs, technical modifications, or long-term high-intensity service, load testing is an important means of verifying continued safe operation. Through regular or condition-based load testing, operational risks can be effectively reduced, service life extended, and long-term stable performance ensured.

As typical heavy-duty lifting equipment, overhead cranes operate for long periods under high loads and high frequencies. Their safety and reliability are directly linked to personnel safety and production continuity. Load testing is a key measure to ensure safe operation under real working conditions, mainly reflected in the following aspects:

Overhead crane load testing usually consists of several test categories. Different test types comprehensively verify the crane from structural, safety, and operational perspectives, ensuring safe and stable performance under actual working conditions. These tests can generally be classified into static load testing, dynamic load testing, and functional coordination and safety device verification.
|
Test Type |
Load Requirement |
Main Test Content |
Core Verification Objective |
Application Stage |
|
Static load testing |
Rated load and specified overload percentage |
Stress and deformation of main girders, end trucks, and structures |
Verify structural strength, stiffness, and load-bearing capacity |
Factory inspection, installation acceptance, after major modification |
|
Dynamic load testing |
Typically rated load |
Hoisting, lowering, crane travel, trolley travel, and braking |
Verify operational smoothness and mechanism coordination |
Factory inspection, after commissioning, before commissioning |
|
Functional coordination testing |
Under rated load |
Multi-mechanism coordinated operation and control logic |
Verify reliability of system coordination |
Installation and commissioning, overall acceptance |
|
Safety device verification |
Simulated actual load conditions |
Overload protection, limit switches, emergency stop devices |
Ensure safety devices function effectively and respond promptly |
Factory inspection, on-site acceptance |
|
Comparison Aspect |
Static Load Testing |
Dynamic Load Testing |
|
Test objective |
Verify the structural strength and stiffness of the overhead crane |
Verify the overall performance of the crane under operating conditions |
|
Applied load |
Typically 110%–125% of the rated load |
Typically 100% of the rated load |
|
Crane condition |
Crane remains stationary |
Crane operates under normal running conditions |
|
Main test content |
Deformation, stress, and elastic recovery of main girders, end trucks, and structures |
Hoisting, lowering, crane travel, trolley travel, and braking performance |
|
Key focus |
Structural safety and load-bearing capacity |
Operational smoothness, braking reliability, and mechanism coordination |
|
Test method |
Load is lifted and held for a specified period, followed by inspection |
Repeated execution of operating motions under load |
|
Risk identification |
Identifies structural design or manufacturing defects |
Identifies issues in mechanisms, control systems, or safety devices |
|
Application stage |
Factory inspection, installation acceptance, after major modification |
Factory inspection, installation and commissioning, pre-commissioning confirmation |

For export projects, applicable standards are usually specified in the contract, with FAT (Factory Acceptance Test) and SAT (Site Acceptance Test) implemented. Customers may require load testing to be witnessed by third parties or classification societies. In addition to static and dynamic load tests, acceptance typically includes braking performance, safety protection devices, non-destructive testing, and complete English test reports and certificates. Contractual requirements generally take precedence over generic standards.

Before load testing, the overhead crane must complete installation and commissioning and pass visual and functional pre-inspections. Key checks include the steel structure, connection bolts, welds, rails, and power supply system, ensuring that hoisting, traveling, braking, limit switches, and emergency stop devices operate correctly.
Standard test loads (weights or equivalent loads) should be prepared according to the rated capacity, with verification of load weight and lifting accessory configuration. A load testing plan should be developed, defining load ratios, test steps, safety measures, and emergency procedures, followed by a safety briefing for on-site personnel.

Testing is generally conducted in the sequence of no-load → rated load → overload.
Throughout the process, impact loading must be avoided, and loads must not exceed design and test specifications.

During testing, test load values, holding time, main girder deflection, elastic recovery, and any abnormal phenomena should be recorded in real time. After unloading from static testing, there should be no permanent deformation. After dynamic testing, all mechanisms should operate normally.
Results are evaluated based on applicable standards and contractual requirements, comparing allowable deflection limits, deformation recovery, and safety device performance, and formal load testing records are issued.

Upon successful load testing, complete documentation should be compiled and submitted, including the test plan, original records, result evaluation sheets, and relevant certificates. For export or critical projects, third-party witness signatures may be included. After final acceptance confirmation, the overhead crane may be commissioned for use or delivered to the customer.

Common issues during load testing include inaccurate test load weights, arbitrary counterweight combinations, or improper selection of lifting accessories.
An unsuitable test environment is one of the most common risk factors, including:
Such deviations can affect crane operating stability and may lead to abnormal vibration, braking failure, or inaccurate test data during load testing, ultimately compromising the reliability of test conclusions.
Load testing must be carried out by qualified personnel with continuous on-site monitoring. Improper operation—such as excessive acceleration during hoisting or traveling, frequent impact braking, or failure to monitor structural deflection and critical components in real time—can easily result in equipment damage or safety incidents. In addition, the absence of clear command structures and emergency measures on site can significantly amplify safety risks when unexpected situations occur.


Load testing is the fundamental safeguard for the safe operation of overhead cranes and a critical step before equipment is put into production. Only through standardized, sufficient, and compliant load testing can the actual load-bearing capacity and operational reliability of a crane be truly verified, ensuring safe, stable, and efficient operation in subsequent use. Passing load testing before commissioning is not only a responsibility to the equipment itself, but also a vital guarantee for personnel safety and production continuity.
When selecting an overhead crane, customers should not only focus on equipment specifications, but also place great importance on the professionalism and execution standards of load testing. With comprehensive testing capabilities, a rigorous quality control system, and extensive project experience, HSCRANE provides reliable support for project delivery and long-term operation.
Contact HSCRANE today to obtain overhead crane load testing solutions and professional technical support that comply with both domestic and international standards, ensuring a safe and smooth start-up for your project.
In addition to standardized load testing, overhead cranes also require effective prevention and maintenance of common operational failures to ensure long-term safe and stable performance—click to read Key Inspection Points and Maintenance Tips for Common Overhead Crane Failures.